At a glance
Electricity in the Cayman Islands is governed by legislation, government policy, utility licences and independent regulatory oversight.
- Government: The Cayman Islands Government establishes the legislative framework and sets national energy policy, including the National Energy Policy 2024–2045.
- Regulator: The Utility Regulation and Competition Office (URCO), independently regulates the electricity sector.
- Utility: Caribbean Utilities Company, Ltd. (CUC) operates Grand Cayman’s public electricity system under its licences and the applicable regulatory framework.
How the electricity sector is regulated
Electricity regulation in the Cayman Islands helps ensure the public electricity system operates within an established framework. It influences how electricity is generated, transmitted and distributed, how utility services are regulated, and how decisions are made about the sector’s future.
In Grand Cayman, Caribbean Utilities Company, Ltd., known as CUC, operates the public electricity system. CUC generates electricity and is responsible for transmitting and distributing it to homes and businesses across the island. These activities are carried out under licences that establish the company’s rights and responsibilities.
The Utility Regulation and Competition Office, known as URCO, provides independent oversight of the electricity sector. Its responsibilities include regulating utility licences, reviewing electricity rates and tariffs, monitoring compliance and overseeing matters relating to the reliability and security of electricity supply. OfReg also has a role in supporting the integration of renewable energy into the electricity system.
The Cayman Islands Government establishes the legislative framework and sets the country’s overall energy policy. This includes the National Energy Policy 2024–2045, which provides direction for the development of the energy sector, with a focus on energy security, renewable energy and more efficient energy use.
What this means for electricity customers
These responsibilities work together to guide the operation and development of Grand Cayman’s electricity system. They influence decisions about electricity rates, infrastructure investment, future generating capacity, service reliability and the introduction of renewable energy.
Understanding the roles of CUC, URCO and the Cayman Islands Government helps customers see how the electricity sector is managed, who is responsible for different decisions and what guides the future of electricity supply in the Cayman Islands.
The roles of Government, the regulator and the utility
The Cayman Islands Government establishes laws and national policies for the electricity sector. Its National Energy Policy 2024–2045, approved by Cabinet on 16 April 2024, sets the country’s long-term energy vision and includes strategies relating to renewable energy, energy efficiency, resilience, affordability and energy security.
URCO administers and enforces the applicable regulatory framework. Its responsibilities include licensing, monitoring compliance, reviewing matters relating to rates and charges, overseeing aspects of generation procurement, monitoring utility performance and supporting the safety, reliability and security of the electricity supply. URCO also advises Government on electricity matters and conducts public consultations on significant regulatory proposals.
CUC operates the electricity system in Grand Cayman. This includes generating electricity, maintaining the transmission and distribution network, connecting customers, restoring service after outages and investing in infrastructure needed to meet demand and maintain reliability.
In simple terms, Government establishes the legislative and policy direction, URCO provides independent regulatory oversight, and CUC operates the electricity system in accordance with its licences and the applicable regulatory framework.
How CUC operates under its licences
CUC operates under two principal electricity licences: a Transmission and Distribution Licence and a non-exclusive Generation Licence.
The Transmission and Distribution Licence gives CUC the exclusive right to transmit and distribute electricity in Grand Cayman. Transmission involves moving electricity at high voltage across the system, while distribution delivers electricity through the network to individual homes and businesses.
Under this licence, CUC maintains and operates the substations, poles, overhead and underground lines, submarine cables and other infrastructure that form Grand Cayman’s electricity network.
CUC’s Generation Licence permits the company to generate electricity, but the licence is non-exclusive. The present Generation Licence was issued on 20 November 2014, replacing the licence granted in 2008.
The non-exclusive nature of generation means that other qualified parties can potentially develop electricity-generation projects. However, this does not create an unrestricted market in which a generator may simply connect to the grid and sell electricity. Projects must comply with the applicable licensing, procurement, technical, planning and regulatory requirements.
How regulation works in practice
Electricity regulation is broader than approving or rejecting individual projects. It establishes the framework within which the electricity system is planned, financed and operated.
Rates and customer charges
An electricity bill contains different components, and those components are not all regulated or adjusted in the same way.
CUC’s published standard billing rates distinguish base-rate components, such as facilities and energy charges, from other items that may appear separately. These can include fuel costs, government fuel duty, renewable-energy purchase costs, licence and regulatory fees and charges for optional services.
For CUC, annual adjustments to base rates are governed by the Rate Cap and Adjustment Mechanism, known as RCAM, contained in the company’s Transmission and Distribution Licence.
The RCAM uses a formula based on 60% Cayman Islands Consumer Price Index and 40% United States Consumer Price Index, excluding food and fuel. URCO verifies the information used in the calculation and determines whether the resulting adjustment complies with the licence.
Licence and regulatory fees are another distinct billing component. CUC describes these fees as a direct pass-through, without an added markup, to customer consumption above the applicable threshold. The fees are reviewed in accordance with the conditions of the Transmission and Distribution Licence.
Planning for new generating capacity
As Grand Cayman develops and electricity demand changes, additional generating capacity may be required to maintain a reliable supply.
The process begins with identifying and demonstrating the system’s capacity requirements. A Certificate of Need is a procedural step under CUC’s Transmission and Distribution Licence and Main Agreement. It establishes the need for additional capacity but does not, by itself, approve a particular technology, developer, project or commercial arrangement.
Once the need has been established through the applicable regulatory process, URCO can proceed with a competitive solicitation. This allows qualified parties to propose solutions that meet the system’s technical, reliability, timing and cost requirements.
Competition therefore applies to opportunities to develop new generation. CUC remains the exclusive transmission and distribution licensee for Grand Cayman and is responsible for operating the grid to which approved generation projects connect.
Renewable energy
Renewable-energy projects operate within the same broader legal, licensing and technical framework as other generation resources.
The National Energy Policy 2024–2045 provides the country’s policy direction for increasing renewable energy, improving efficiency and supporting long-term energy security. URCO performs its regulatory functions within the applicable legislative and policy framework, while CUC is responsible for safely integrating approved generation into the Grand Cayman electricity system.
This means that adding renewable energy is not solely a decision by either the regulator or the utility. It can involve Government policy, regulatory processes, system planning, competitive procurement, licensing, commercial agreements, grid-integration studies and construction.
How utility-scale solar fits into the process
A utility-scale solar farm is a major electricity-generation project designed to supply power to the grid rather than primarily serving one home or business.
In July 2025, URCO launched a request for proposals for a utility-scale solar and battery-storage project designed to provide 22.5 megawatts of dispatchable renewable-energy capacity.
Battery storage is an important part of this type of project because it allows energy generated during daylight hours to be stored and dispatched when required. This can help renewable generation contribute to peak demand and support grid stability when solar production is reduced or unavailable.
In a competitive solicitation, URCO oversees the regulatory procurement process. CUC contributes system forecasts, operational information and technical requirements, evaluates how proposed resources would integrate with the grid as required by the process, and ultimately operates the transmission and distribution system to which an approved project would connect.
Any selected project must still complete the applicable regulatory, contractual, technical, planning and construction steps before it can begin supplying electricity.
Why electricity regulation matters
Electricity regulation is intended to balance several important priorities.
Customers need a safe, dependable service and clear information about what they are being charged. The electricity system must also have sufficient generating capacity and resilient transmission and distribution infrastructure to meet demand.
At the same time, the utility must be able to make prudent investments, operate and maintain the system, meet its licence obligations and earn a fair and reasonable return. The sector must also support national goals relating to renewable energy, affordability, efficiency and energy security.
Independent regulation provides a framework for balancing these objectives. It establishes obligations, monitors performance, supports transparent decision-making and provides processes through which major regulatory proposals may be considered.
What regulation means for customers
For customers in Grand Cayman, CUC is the company that generates and delivers electricity, maintains the grid, manages customer accounts and restores service when outages occur.
URCO independently oversees the regulated electricity sector. The Cayman Islands Government establishes the legislative framework and sets national energy policy.
This arrangement means that significant decisions about rates, new generating capacity, electricity infrastructure and renewable-energy integration are addressed through established legal, licensing and regulatory processes. These processes are designed to support a safe, reliable and economically sustainable electricity service while protecting the long-term interests of consumers.
Frequently asked questions
Who regulates electricity in the Cayman Islands?
The electricity sector is independently regulated by the Utility Regulation and Competition Office, legally referred to as URCO. Its responsibilities include licensing, compliance, aspects of rates and charges, utility performance, service reliability and processes for procuring new generating capacity. The Cayman Islands Government establishes the underlying legislation and national energy-policy direction.
What is CUC’s role?
CUC operates Grand Cayman’s public electricity system. It generates electricity and holds the exclusive licence to transmit and distribute electricity on the island. It also maintains the grid, connects and serves customers, plans for system requirements and operates in accordance with its licences and the applicable regulatory framework.
Can other companies generate electricity in Grand Cayman?
Yes. CUC’s Generation Licence is non-exclusive, so other qualified parties may develop generation projects. However, they must satisfy the applicable procurement, licensing, technical and regulatory requirements. CUC remains the exclusive transmission and distribution licensee in Grand Cayman.
How is new utility-scale generation procured?
New utility-scale generation is procured through the applicable planning and regulatory process, which can include a competitive solicitation overseen by URCO. The need for additional capacity must first be established through the applicable planning and regulatory process. Where the licence framework requires a competitive solicitation, URCO can invite qualified parties to submit proposals and evaluate the available options through the required regulatory steps. Approval of a Certificate of Need does not amount to approval of a particular project or technology.
How is utility-scale solar procured?
Utility-scale solar may be procured through a competitive process overseen by URCO. In 2025, URCO launched a request for proposals for a solar and battery-storage project intended to supply 22.5 megawatts of dispatchable renewable-energy capacity.
How are electricity rates and charges regulated?
CUC’s base rates are adjusted annually under a formula contained in its Transmission and Distribution Licence, and URCO verifies whether each adjustment complies with the licence. Different components of a customer’s bill are treated differently. CUC’s annual base-rate adjustment is governed by the RCAM formula contained in its Transmission and Distribution Licence, while other proposed rate changes can require separate regulatory review and approval. Fuel costs, government fuel duty, renewable-energy purchase costs and licence and regulatory fees are separately identified billing components and should not be described as part of the base rate.
What is URCO?
URCO is the Utility Regulation and Competition Office, which independently regulates the electricity sector in the Cayman Islands. It is legally referred to as URCO and commonly known as OfReg. URCO administers and enforces the applicable regulatory framework, advises Government on electricity matters and conducts public consultations on significant regulatory proposals.
Is OfReg the same as URCO?
Yes. The Utility Regulation and Competition Office is legally referred to as URCO and commonly known as OfReg. Both names refer to the same independent regulator.
What is the National Energy Policy 2024–2045?
The National Energy Policy 2024–2045 is the Cayman Islands Government’s national energy policy, approved by Cabinet on 16 April 2024. It sets the country’s long-term energy vision and includes strategies relating to renewable energy, energy efficiency, resilience, affordability and energy security.
What is the Rate Cap and Adjustment Mechanism (RCAM)?
The RCAM governs annual adjustments to CUC’s base rates and is contained in the company’s Transmission and Distribution Licence. It uses a formula based on 60% Cayman Islands Consumer Price Index and 40% United States Consumer Price Index, excluding food and fuel. URCO verifies the information used in the calculation and determines whether the resulting adjustment complies with the licence.
What is a Certificate of Need?
A Certificate of Need is a procedural step under CUC’s Transmission and Distribution Licence and Main Agreement. It establishes the need for additional generating capacity but does not, by itself, approve a particular technology, developer, project or commercial arrangement.